構造 69
-
構造 こうぞう
ENstructureVIkết cấu
The load-bearing system of a building that carries loads down to the foundation.
-
荷重 かじゅう
ENloadVItải trọng
A force acting on a structure, such as self-weight, occupancy, wind or earthquake.
-
固定荷重 こていかじゅう
ENdead loadVItĩnh tải
Permanent load from the self-weight of the structure and finishes.
-
積載荷重 せきさいかじゅう
ENlive loadVIhoạt tải
Variable load from people, furniture and equipment using the building.
-
地震荷重 じしんかじゅう
ENseismic loadVItải trọng động đất
Lateral force on a building caused by ground shaking during an earthquake.
-
風荷重 ふうかじゅう
ENwind loadVItải trọng gió
Pressure or suction exerted by wind on building surfaces.
-
積雪荷重 せきせつかじゅう
ENsnow loadVItải trọng tuyết
Load from accumulated snow on roofs, significant in Japan's snowy regions.
-
柱 はしら
ENcolumnVIcột
A vertical member in compression that transfers loads from beams to the foundation.
-
梁 はり
ENbeamVIdầm
A horizontal member in bending that supports slabs and transfers loads to columns.
-
大梁 おおばり
ENgirderVIdầm chính
A main beam spanning between columns that supports secondary beams.
-
小梁 こばり
ENsecondary beamVIdầm phụ
A smaller beam framing into girders that directly supports the slab.
-
床スラブ ゆかスラブ
ENslabVIsàn (bản sàn)
A flat horizontal concrete plate forming a floor or roof that carries loads directly.
-
耐力壁 たいりょくへき
ENload-bearing wallVItường chịu lực
A wall designed to resist vertical loads and lateral forces such as earthquakes.
-
耐震壁 たいしんへき
ENshear wallVIvách cứng
A reinforced concrete wall that mainly resists lateral seismic and wind forces.
-
筋かい すじかい
ENbraceVIgiằng chéo
A diagonal member placed in a frame to increase lateral stiffness.
-
ラーメン構造 ラーメンこうぞう
ENrigid frameVIkhung cứng
A frame of columns and beams with moment-resisting joints that resist lateral loads.
-
鉄筋コンクリート てっきんコンクリート
ENreinforced concreteVIbê tông cốt thép (BTCT)
Concrete with embedded steel reinforcement; abbreviated RC in Japan.
-
鉄骨造 てっこつぞう
ENsteel structureVIkết cấu thép
A building whose frame is made of structural steel sections; called S-zō in Japan.
-
鉄骨鉄筋コンクリート造 てっこつてっきんコンクリートぞう
ENSRCVIbê tông cốt thép liên hợp thép hình
Steel Reinforced Concrete: structural steel encased in reinforced concrete.
-
木造 もくぞう
ENwooden structureVIkết cấu gỗ
A building with a timber load-bearing system, common in Japanese housing.
-
ENconcreteVIbê tông
A hardened mixture of cement, aggregate and water that is strong in compression.
-
生コンクリート なまコンクリート
ENready-mixed concreteVIbê tông tươi (bê tông thương phẩm)
Concrete batched at a plant and delivered by mixer truck; often called nama-kon.
-
ENcementVIxi măng
A powdered binder that hardens through reaction with water.
-
骨材 こつざい
ENaggregateVIcốt liệu
Sand, gravel or crushed stone mixed into concrete or mortar.
-
ENmortarVIvữa
A mixture of cement, sand and water used for masonry and plastering.
-
ENslumpVIđộ sụt
A measure of fresh concrete workability obtained by the slump cone test.
-
設計基準強度 せっけいきじゅんきょうど
ENdesign strengthVIcường độ thiết kế
The concrete compressive strength assumed as the basis of structural design (Fc).
-
圧縮強度 あっしゅくきょうど
ENcompressive strengthVIcường độ chịu nén
The maximum compressive stress a material can withstand before failure.
-
水セメント比 みずセメントひ
ENwater-cement ratioVItỉ lệ nước/xi măng
The mass ratio of water to cement, governing concrete strength and durability.
-
養生 ようじょう
ENcuringVIbảo dưỡng bê tông
Keeping placed concrete moist and at suitable temperature so it gains strength.
-
ENcold jointVImạch ngừng nguội
A weak joint formed when fresh concrete is placed on concrete that has already set.
-
ENhoneycombVIrỗ tổ ong
A concrete defect of exposed voids and aggregate caused by poor compaction or grout loss.
-
ひび割れ ひびわれ
ENcrackVIvết nứt
A fracture line in concrete caused by shrinkage, temperature or overload.
-
鉄筋 てっきん
ENrebarVIcốt thép (sắt)
Steel bars embedded in concrete to resist tension.
-
異形鉄筋 いけいてっきん
ENdeformed barVIthép gân (thép vằn)
Rebar with surface ribs for better bond, designated D in Japan (D13, D16).
-
主筋 しゅきん
ENmain reinforcementVIthép chủ
The principal longitudinal bars carrying tension or compression in columns and beams.
-
帯筋 おびきん
ENhoopVIthép đai cột
Ties around column main bars that resist shear and restrain buckling; also called hoop.
-
あばら筋 あばらきん
ENstirrupVIthép đai dầm
Closed ties around beam main bars to resist shear; also called stirrup.
-
かぶり厚さ かぶりあつさ
ENconcrete coverVIlớp bê tông bảo vệ
The distance from the outer surface of reinforcement to the concrete surface.
-
ENspacerVIcon kê (cục kê)
A concrete or plastic block that keeps the specified cover to reinforcement.
-
重ね継手 かさねつぎて
ENlap spliceVInối chồng
A rebar splice made by overlapping two bars for a specified length.
-
ガス圧接 ガスあっせつ
ENgas pressure weldingVIhàn ép hơi
A rebar joining method heating bar ends and pressing them axially, common in Japan.
-
定着 ていちゃく
ENanchorageVIneo cốt thép
Embedment of a bar into another member so force transfers without pull-out.
-
結束線 けっそくせん
ENbinding wireVIdây kẽm buộc
Soft wire used to tie reinforcing bars together.
-
H形鋼 エイチがたこう
ENH-section steelVIthép hình H
A rolled steel section with an H-shaped profile, widely used for columns and beams.
-
角形鋼管 かくがたこうかん
ENsquare steel tubeVIthép hộp vuông
A square hollow steel section, commonly used for steel columns in Japan.
-
高力ボルト こうりょくボルト
ENhigh-strength boltVIbu lông cường độ cao
A high-tension bolt used for friction connections of steel members.
-
ENanchor boltVIbu lông neo
A bolt embedded in a foundation to fix column bases or equipment.
-
溶接 ようせつ
ENweldingVIhàn
Joining metals by local melting.
-
ENbase plateVIbản đế chân cột
A steel plate at a column base that transfers loads to the foundation via anchor bolts.
-
ENdiaphragmVItấm cứng (diaphragm)
A stiffening plate inside a tube column at beam connections.
-
耐火被覆 たいかひふく
ENfireproof coveringVIlớp bọc chống cháy
A coating on structural steel that slows temperature rise during a fire.
-
基礎 きそ
ENfoundationVImóng
The lowest part of a building that transfers loads to the ground.
-
独立基礎 どくりつきそ
ENspread footingVImóng đơn
An individual footing placed under a single column.
-
布基礎 ぬのきそ
ENstrip footingVImóng băng
A continuous footing running under walls or a row of columns.
-
べた基礎 べたきそ
ENmat foundationVImóng bè
A concrete slab foundation covering the entire building footprint.
-
杭 くい
ENpileVIcọc
A long member driven or bored into the ground to carry loads to firm strata.
-
場所打ち杭 ばしょうちぐい
ENcast-in-place pileVIcọc khoan nhồi
A pile formed by boring a hole, inserting a rebar cage and casting concrete in place.
-
地中梁 ちちゅうばり
ENfooting beamVIdầm móng
A beam below grade linking footings to resist differential settlement.
-
地耐力 ちたいりょく
ENbearing capacityVIsức chịu tải của đất nền
The ability of ground to support loads without failure or excessive settlement.
-
沈下 ちんか
ENsettlementVIlún
Downward movement of a foundation due to soil compression.
-
液状化 えきじょうか
ENliquefactionVIhóa lỏng nền đất
Loss of strength in saturated sandy soil during earthquake shaking.
-
免震 めんしん
ENseismic isolationVIcách chấn
Placing isolators between foundation and superstructure to reduce seismic motion.
-
耐震 たいしん
ENearthquake-resistantVIkháng chấn
Designed with enough strength and stiffness to withstand earthquakes.
-
耐震補強 たいしんほきょう
ENseismic retrofitVIgia cố kháng chấn
Strengthening an existing building to improve its earthquake resistance.
-
ENdeflectionVIđộ võng
The displacement of a beam or slab under load.
-
曲げモーメント まげモーメント
ENbending momentVImô men uốn
The internal force causing a member to bend, governing tensile reinforcement.
-
せん断力 せんだんりょく
ENshear forceVIlực cắt
An internal force tending to slide one part of a member past another.
-
構造計算 こうぞうけいさん
ENstructural calculationVItính toán kết cấu
Calculating member forces and checking capacity against code requirements.
施工 69
-
建設現場 けんせつげんば
ENconstruction siteVIcông trường
The place where a building is constructed; often just called genba in Japan.
-
施工 せこう
ENconstruction workVIthi công
Carrying out building work according to drawings and specifications.
-
ENgeneral contractorVItổng thầu
The main contractor responsible for the whole project and coordinating subcontractors.
-
協力会社 きょうりょくがいしゃ
ENsubcontractorVIthầu phụ
A company doing part of the work for the main contractor; also called shitauke.
-
職長 しょくちょう
ENsite foremanVIđội trưởng (tổ trưởng)
The person directly leading a crew of workers on site.
-
職人 しょくにん
ENcraftsmanVIthợ (tay nghề)
A skilled tradesperson such as a formworker or rebar fixer.
-
準備工事 じゅんびこうじ
ENsite preparationVIchuẩn bị mặt bằng
Work before main construction: hoarding, site huts and temporary utilities.
-
仮設工事 かせつこうじ
ENtemporary worksVIcông trình tạm
Temporary facilities for construction, such as scaffolding and fencing, later removed.
-
仮囲い かりがこい
ENhoardingVIhàng rào công trường
A temporary fence around a site to keep out the public and reduce dust and noise.
-
墨出し すみだし
ENsetting outVIđịnh vị (phóng tuyến)
Marking grid lines and levels on site so work is built in the correct position.
-
墨 すみ
ENreference lineVIđường mực chuẩn
A chalk or ink line marked as a positioning reference, such as an offset line.
-
ENbenchmarkVImốc cao độ
A point of known elevation used as the level reference for a project (BM).
-
掘削 くっさく
ENexcavationVIđào đất
Removing soil to build foundations or basements.
-
埋戻し うめもどし
ENbackfillVIlấp đất
Placing and compacting soil back around completed foundations.
-
締固め しめかため
ENcompactionVIđầm nén
Densifying soil or concrete to remove voids.
-
山留め やまどめ
ENearth retainingVIchắn giữ thành hố đào
Temporary structure that prevents excavation walls from collapsing.
-
鋼矢板 こうやいた
ENsheet pileVIcừ thép (cừ Larsen)
Interlocking steel sheets driven in a line to retain soil and water.
-
排水工事 はいすいこうじ
ENdewateringVIhạ mực nước ngầm
Pumping groundwater to keep an excavation dry during work.
-
捨てコンクリート すてコンクリート
ENlean concreteVIbê tông lót
A thin concrete layer under footings giving a clean, level surface for marking.
-
砕石地業 さいせきじぎょう
ENcrushed stone baseVIlớp đá dăm lót
A compacted layer of crushed stone placed beneath footings or ground slabs.
-
型枠 かたわく
ENformworkVIcốp pha (ván khuôn)
A temporary mould that shapes concrete until it hardens.
-
ENplywood form panelVIván ép cốp pha
Plywood sheet used as form facing, commonly 900×1800 mm.
-
ENform tieVIty giằng cốp pha
A steel rod holding opposite form faces at the correct spacing; called sepa.
-
ENform clampVIbát chống cốp pha (khóa cốp pha)
A fastener screwed onto a form tie to clamp the walers.
-
支保工 しほこう
ENshoringVIcây chống (chống đỡ)
Temporary supports for slab and beam forms during concreting and curing.
-
ENpipe supportVIcây chống thép điều chỉnh
An adjustable steel tube prop supporting slab formwork.
-
脱型 だっけい
ENform removalVItháo cốp pha
Stripping formwork once concrete reaches the required strength.
-
コンクリート打設 コンクリートだせつ
ENconcrete placingVIđổ bê tông
Placing fresh concrete into forms and compacting it.
-
コンクリートポンプ車 コンクリートポンプしゃ
ENconcrete pump truckVIxe bơm bê tông
A truck with a boom and pump that delivers concrete to the pour location.
-
アジテーター車 アジテーターしゃ
ENtruck mixerVIxe bồn trộn bê tông
A truck carrying fresh concrete in a rotating drum; also called mixer truck.
-
ENconcrete vibratorVImáy đầm dùi
A poker that vibrates fresh concrete to release air and compact it.
-
金ごて仕上げ かなごてしあげ
ENtrowel finishingVIxoa mặt bê tông
Smoothing a concrete slab surface with a steel trowel.
-
配筋 はいきん
ENrebar placingVIlắp đặt cốt thép
Arranging and tying reinforcement per drawings before concreting.
-
鉄骨建方 てっこつたてかた
ENsteel erectionVIdựng kết cấu thép
Erecting steel columns and beams on site with cranes.
-
建入れ直し たていれなおし
ENplumbing adjustmentVIchỉnh thẳng đứng
Adjusting erected steel columns to be truly vertical.
-
足場 あしば
ENscaffoldingVIgiàn giáo
A temporary structure providing working platforms at height.
-
枠組足場 わくぐみあしば
ENframe scaffoldingVIgiàn giáo khung
Scaffolding assembled from standard frames, cross braces and decks.
-
くさび緊結式足場 くさびきんけつしきあしば
ENsystem scaffoldingVIgiàn giáo nêm
Wedge-lock scaffolding, quick to assemble, common on low-rise work.
-
足場板 あしばいた
ENscaffold boardVIsàn thao tác (tấm sàn giáo)
A plank or steel deck laid on scaffolding as a walking surface.
-
幅木 はばき
ENtoe boardVItấm chắn chân
A low edge board on a platform that prevents objects falling.
-
足場組立て あしばくみたて
ENscaffold erectionVIlắp dựng giàn giáo
Assembling scaffolding in sequence according to approved drawings.
-
ENmobile scaffoldVIgiàn giáo di động
A wheeled scaffold tower used for indoor work.
-
脚立 きゃたつ
ENstepladderVIthang chữ A
A self-supporting folding ladder for low-height work.
-
ENtower craneVIcần trục tháp
A tall fixed crane used to lift materials on high-rise projects.
-
ENmobile craneVIcần cẩu bánh lốp
A rough-terrain mobile crane, called rafutā, very common on Japanese sites.
-
ENexcavatorVImáy đào
A hydraulic backhoe excavator; also called yunbo in Japan.
-
ENbulldozerVImáy ủi
A machine with a front blade for pushing and levelling soil.
-
ENdump truckVIxe ben
A truck with a tipping body for unloading soil or materials.
-
ENforkliftVIxe nâng
A vehicle with forks for lifting palletised loads.
-
高所作業車 こうしょさぎょうしゃ
ENaerial work platformVIxe nâng người
A vehicle with a raised platform lifting workers to height.
-
工事用エレベーター こうじようエレベーター
ENconstruction hoistVIvận thăng
A temporary lift carrying workers and materials up the building.
-
ENrammerVImáy đầm cóc
A jumping compactor used for soil in confined areas.
-
ENplate compactorVImáy đầm bàn
A vibrating plate machine for compacting sand and gravel.
-
ENdisc grinderVImáy mài cầm tay
A hand-held rotating disc tool for cutting and grinding metal.
-
ENimpact driverVImáy bắt vít
A power tool driving screws and bolts with rotary impacts.
-
ENlevelVImáy thủy bình
A surveying instrument measuring height differences.
-
レーザー墨出し器 レーザーすみだしき
ENlaser levelVImáy cân mực laser
A device projecting horizontal and vertical laser lines for marking.
-
墨つぼ すみつぼ
ENchalk lineVIbật mực
A tool with an inked string snapped to mark straight lines.
-
仕上げ工事 しあげこうじ
ENfinishing workVIcông tác hoàn thiện
Surface work such as plastering, painting, tiling and ceilings.
-
左官工事 さかんこうじ
ENplasteringVItrát
Applying mortar or plaster to walls and floors, done by sakan plasterers.
-
塗装 とそう
ENpaintingVIsơn
Applying paint to protect and decorate surfaces.
-
タイル工事 タイルこうじ
ENtilingVIốp lát gạch
Fixing ceramic tiles to walls and floors with mortar or adhesive.
-
防水工事 ぼうすいこうじ
ENwaterproofingVIchống thấm
Applying water barriers to roofs, wet areas and basements.
-
ENsealantVIkeo trám khe
An elastic material filling joints to keep out water and air.
-
内装工事 ないそうこうじ
ENinterior finishingVIhoàn thiện nội thất
Building partitions, ceilings, floors and interior finishes.
-
軽量鉄骨下地 けいりょうてっこつしたじ
ENlight-gauge steel studVIkhung xương thép nhẹ
Thin galvanized steel framing for partitions and ceilings; called LGS or keitetsu.
-
石膏ボード せっこうボード
ENplasterboardVItấm thạch cao
Paper-faced gypsum board used for walls and ceilings.
-
解体工事 かいたいこうじ
ENdemolitionVIphá dỡ
Taking down all or part of a building.
-
片付け かたづけ
ENcleanupVIdọn dẹp vệ sinh
Clearing materials and debris after work, paired with seiri-seiton.
安全・現場コミュニケーション 66
-
安全第一 あんぜんだいいち
ENsafety firstVIan toàn là trên hết
The core slogan of Japanese sites, putting safety before schedule.
-
朝礼 ちょうれい
ENmorning assemblyVIhọp đầu giờ (chào buổi sáng)
The start-of-day gathering for exercises, work announcements and safety notes.
-
ラジオ体操 ラジオたいそう
ENradio calisthenicsVIthể dục buổi sáng
Standard warm-up exercises done to music at the morning assembly.
-
KY活動 ケーワイかつどう
ENKY activityVIhoạt động dự đoán nguy hiểm (KY)
Kiken Yochi (hazard prediction): the crew identifies the day's hazards and agrees countermeasures.
-
KYシート ケーワイシート
ENKY sheetVIphiếu KY
A form recording the task, hazards, countermeasures and crew signatures.
-
指差し呼称 ゆびさしこしょう
ENpointing and callingVIchỉ tay hô to
Pointing at an item and calling out to confirm it, e.g. 'Harness, OK!'.
-
ENtouch and callVIchạm tay hô khẩu hiệu
The crew stacks hands and shouts a safety slogan after KY.
-
ENtoolbox meetingVIhọp an toàn tổ (TBM)
A short crew meeting before work to assign tasks and review safety; abbreviated TBM.
-
ENnear missVIsuýt xảy ra tai nạn
An incident that almost caused an accident, reported to prevent recurrence.
-
労働災害 ろうどうさいがい
ENoccupational accidentVItai nạn lao động
Injury or illness of a worker arising from work; called rōsai.
-
四大災害 よんだいさいがい
ENfour major hazardsVIbốn loại tai nạn chính
Falls, falling objects, collapse and machinery accidents, the leading fatal accidents in construction.
-
墜落 ついらく
ENfall from heightVIngã từ trên cao
A person falling from height, the most common fatal site accident.
-
転倒 てんとう
ENslip and fallVItrượt ngã
Falling on the same level due to slipping or tripping.
-
落下物 らっかぶつ
ENfalling objectVIvật rơi
Tools or materials dropping from height that can injure people below.
-
倒壊 とうかい
ENcollapseVIsập đổ
Failure and collapse of temporary works, scaffolding or excavation walls.
-
挟まれ・巻き込まれ はさまれ・まきこまれ
ENcaught in machineryVIbị kẹp, cuốn vào máy
Being trapped between objects or drawn into rotating machine parts.
-
感電 かんでん
ENelectric shockVIđiện giật
Electric current passing through the body on contact with live parts.
-
熱中症 ねっちゅうしょう
ENheatstrokeVIsay nắng (sốc nhiệt)
Illness from overheating and dehydration during summer outdoor work.
-
暑さ指数 あつさしすう
ENWBGTVIchỉ số nhiệt WBGT
Wet Bulb Globe Temperature, an index combining heat, humidity and radiation to gauge heatstroke risk.
-
保護具 ほごぐ
ENPPEVIđồ bảo hộ cá nhân
Personal Protective Equipment such as helmets, glasses, gloves, boots and harnesses.
-
ENhard hatVImũ bảo hộ
A rigid helmet protecting the head from falling objects; chin strap must be fastened.
-
ENchin strapVIquai mũ
A strap under the chin that keeps the helmet in place.
-
フルハーネス型墜落制止用器具 フルハーネスがたついらくせいしようきぐ
ENfull-body harnessVIdây an toàn toàn thân
A harness around shoulders, chest and thighs, mandatory for work at height in Japan.
-
安全帯 あんぜんたい
ENsafety beltVIdây đai an toàn
The traditional term for fall-arrest equipment, still used colloquially on site.
-
ENlanyard hookVImóc dây an toàn
The hook at the lanyard end attached to an anchor or lifeline.
-
親綱 おやづな
ENlifelineVIdây cứu sinh
A horizontal rope used as an attachment line for harness hooks at height.
-
安全靴 あんぜんぐつ
ENsafety shoesVIgiày bảo hộ
Boots with steel toecaps and puncture-resistant soles.
-
保護メガネ ほごメガネ
ENsafety glassesVIkính bảo hộ
Glasses protecting eyes from dust and debris when cutting or grinding.
-
防じんマスク ぼうじんマスク
ENdust maskVIkhẩu trang chống bụi
A respirator filtering fine dust during concrete cutting or demolition.
-
軍手 ぐんて
ENwork glovesVIgăng tay lao động
Cotton work gloves; not worn near rotating machines due to entanglement risk.
-
安全ベスト あんぜんベスト
ENreflective vestVIáo phản quang
A vest with reflective strips that makes the wearer visible.
-
耳栓 みみせん
ENear plugsVInút bịt tai
Inserts that reduce noise to protect hearing.
-
手すり てすり
ENguardrailVIlan can an toàn
A rail at platform or slab edges preventing falls.
-
開口部養生 かいこうぶようじょう
ENopening coverVInắp che lỗ mở
A cover or barrier over floor openings to prevent falls.
-
安全ネット あんぜんネット
ENsafety netVIlưới an toàn
A net strung below work areas to catch falling people or objects.
-
養生シート ようじょうシート
ENdebris nettingVIlưới che giàn giáo
Mesh sheeting on scaffolding that stops debris and dust escaping.
-
立入禁止 たちいりきんし
ENno-entry areaVIkhu vực cấm vào
A barricaded zone that only authorised people may enter.
-
ENbarricade coneVIcọc tiêu (nón giao thông)
A plastic traffic cone used to mark off hazard zones.
-
高所作業 こうしょさぎょう
ENwork at heightVIlàm việc trên cao
Work at 2 m or higher, requiring fall-prevention measures.
-
玉掛け たまがけ
ENslingingVImóc cáp (móc tải)
Attaching loads to a crane hook with slings; requires a tamakake licence.
-
ENwire rope slingVIcáp treo
A steel wire rope used to sling loads for lifting.
-
合図 あいず
ENhand signalVIra hiệu bằng tay
Agreed hand or whistle signals between slinger and crane operator.
-
合図者 あいずしゃ
ENsignal personVIngười ra hiệu
The designated person who gives signals to crane or machine operators.
-
巻き上げ まきあげ
ENhoist upVIkéo lên (cẩu lên)
The signal to raise the crane hook.
-
巻き下げ まきさげ
ENlower downVIhạ xuống
The signal to lower the crane hook.
-
ENstopVIdừng lại
The signal to halt all movement immediately.
-
吊り荷の下 つりにのした
ENunder suspended loadVIdưới vật đang treo
The danger zone beneath a lifted load, which must never be entered.
-
始業点検 しぎょうてんけん
ENstart-of-work inspectionVIkiểm tra trước khi làm việc
Checking machines and tools at the start of the shift before use.
-
安全パトロール あんぜんパトロール
ENsafety patrolVItuần tra an toàn
Walking the site to find and correct unsafe conditions.
-
4S よんエス
EN4SVI4S (sàng lọc, sắp xếp, sạch sẽ, săn sóc)
Seiri, Seiton, Seisō, Seiketsu: sort, set in order, shine and standardise the workplace.
-
整理整頓 せいりせいとん
ENtidying upVIsắp xếp gọn gàng
Removing unneeded items and putting needed ones in place to prevent trips.
-
電源遮断 でんげんしゃだん
ENlockoutVIkhóa nguồn (cắt điện an toàn)
Isolating and locking energy sources before servicing machinery.
-
漏電遮断器 ろうでんしゃだんき
ENearth leakage breakerVIaptomat chống giật
A device that cuts power on detecting leakage current, preventing shock.
-
消火器 しょうかき
ENfire extinguisherVIbình chữa cháy
A portable device for putting out small fires.
-
火気作業 かきさぎょう
ENhot workVIcông việc phát lửa
Work producing heat or sparks, like welding, requiring a permit and extinguisher.
-
酸素欠乏 さんそけつぼう
ENoxygen deficiencyVIthiếu oxy
Air with less than 18% oxygen in pits or confined spaces; called sanketsu.
-
新規入場者教育 しんきにゅうじょうしゃきょういく
ENnew entrant educationVIđào tạo người mới vào công trường
Induction on site rules and hazards for workers entering for the first time.
-
特別教育 とくべつきょういく
ENspecial educationVIđào tạo đặc biệt
Legally required training before hazardous tasks such as harness use.
-
技能講習 ぎのうこうしゅう
ENskill training courseVIkhóa học kỹ năng (chứng chỉ)
A licensing course for operations such as forklifts, slinging or scaffolding.
-
健康チェック けんこうチェック
ENhealth checkVIkiểm tra sức khỏe
Checking each worker's health and sleep at the morning assembly.
-
報連相 ほうれんそう
ENreport, contact, consultVIbáo cáo, liên lạc, thảo luận
The communication rule to report, inform and consult superiors promptly.
-
お疲れ様です おつかれさまです
ENthank you for your hard workVIanh/chị vất vả rồi
A common greeting when meeting or finishing work on site.
-
危ない あぶない
ENwatch outVIcoi chừng! (nguy hiểm)
A shout warning of immediate danger.
-
通ります とおります
ENcoming throughVIxin nhường đường
Said when carrying materials past others so they make way.
-
緊急連絡 きんきゅうれんらく
ENemergency contactVIliên lạc khẩn cấp
Contacting supervisors and calling 119 immediately after an accident.
-
安全衛生計画 あんぜんえいせいけいかく
ENsafety and health planVIkế hoạch an toàn vệ sinh lao động
A plan setting occupational safety and health goals and measures for a project.
工事管理 69
-
発注者 はっちゅうしゃ
ENownerVIchủ đầu tư
The party commissioning and paying for the project; also called seshu.
-
請負者 うけおいしゃ
ENcontractorVInhà thầu
The party contracted to carry out construction.
-
設計者 せっけいしゃ
ENdesignerVIđơn vị thiết kế
The architect or firm preparing the design documents.
-
工事監理者 こうじかんりしゃ
ENsupervising engineerVItư vấn giám sát
The person checking, on the owner's behalf, that work matches the design.
-
現場代理人 げんばだいりにん
ENsite managerVIchỉ huy trưởng công trường
The contractor's representative managing the whole site.
-
現場監督 げんばかんとく
ENsite supervisorVIkỹ sư giám sát thi công
The contractor's engineer managing daily progress, quality and safety.
-
主任技術者 しゅにんぎじゅつしゃ
ENchief engineerVIkỹ sư chủ nhiệm kỹ thuật
A licensed engineer legally required on site under the Construction Business Act.
-
施工管理の4大管理 せこうかんりのよんだいかんり
ENfour key controlsVIbốn mục quản lý chính
Quality, cost, schedule and safety management (QCDS).
-
施工管理 せこうかんり
ENconstruction managementVIquản lý thi công
Planning and controlling construction for quality, cost, schedule and safety.
-
図面 ずめん
ENdrawingVIbản vẽ
A graphic document showing the shape and dimensions of a building.
-
設計図 せっけいず
ENdesign drawingsVIbản vẽ thiết kế
The drawing set by the designer forming the basis of the contract.
-
施工図 せこうず
ENshop drawingVIbản vẽ thi công (shop drawing)
A detailed drawing prepared by the contractor for actual site work.
-
意匠図 いしょうず
ENarchitectural drawingsVIbản vẽ kiến trúc
Drawings showing layout, elevations and finishes.
-
構造図 こうぞうず
ENstructural drawingsVIbản vẽ kết cấu
Drawings showing columns, beams, slabs, foundations and reinforcement.
-
設備図 せつびず
ENMEP drawingsVIbản vẽ cơ điện (MEP)
Mechanical, Electrical and Plumbing drawings for building services.
-
平面図 へいめんず
ENfloor planVImặt bằng
A horizontal view showing room layout on one floor.
-
立面図 りつめんず
ENelevationVImặt đứng
A vertical view showing the exterior faces of a building.
-
断面図 だんめんず
ENsectionVImặt cắt
A vertical cut through a building showing heights and construction.
-
詳細図 しょうさいず
ENdetail drawingVIbản vẽ chi tiết
A large-scale drawing showing construction of a specific location.
-
通り芯 とおりしん
ENgrid lineVItrục (lưới trục)
Numbered and lettered reference lines locating columns and walls.
-
縮尺 しゅくしゃく
ENscaleVItỉ lệ
The ratio of drawing size to real size, e.g. 1:100.
-
FL エフエル
ENfloor levelVIcao độ sàn (FL)
Floor Level: the finished floor elevation used as a level reference.
-
GL ジーエル
ENground levelVIcao độ mặt đất (GL)
Ground Level: the reference ground elevation of the site.
-
仕様書 しようしょ
ENspecificationsVIchỉ dẫn kỹ thuật
Documents specifying materials, standards and methods of construction.
-
BIM ビム
ENBIMVImô hình thông tin công trình (BIM)
Building Information Modeling, a data-rich 3D model for design, construction and operation.
-
見積 みつもり
ENestimateVIdự toán (báo giá)
A calculation of construction cost for quoting or budgeting.
-
積算 せきさん
ENquantity takeoffVIbóc tách khối lượng
Measuring quantities of materials and work from drawings for an estimate.
-
数量書 すうりょうしょ
ENbill of quantitiesVIbảng khối lượng
An itemised list of work quantities.
-
単価 たんか
ENunit priceVIđơn giá
The price per unit of work or material.
-
工事費 こうじひ
ENconstruction costVIchi phí xây dựng
The total cost of carrying out the works.
-
諸経費 しょけいひ
ENoverheadVIchi phí chung
Indirect costs such as management, site office and insurance.
-
実行予算 じっこうよさん
ENbudgetVIngân sách
The contractor's internal working budget for cost control.
-
工程 こうてい
ENscheduleVItiến độ
The sequence and timing of work activities.
-
全体工程表 ぜんたいこうていひょう
ENmaster scheduleVItiến độ tổng thể
The schedule for the whole project from start to handover.
-
週間工程表 しゅうかんこうていひょう
ENweekly scheduleVItiến độ tuần
A detailed day-by-day work plan for the week.
-
ENGantt chartVIsơ đồ ngang (Gantt)
A bar chart showing activity durations; called bar chart in Japan.
-
ENcritical pathVIđường găng
The longest chain of activities determining project duration.
-
工期 こうき
ENconstruction periodVIthời gian thi công
The contract period from start to completion.
-
地鎮祭 じちんさい
ENgroundbreaking ceremonyVIlễ động thổ
A Shinto ceremony praying for safety before construction starts.
-
着工 ちゃっこう
ENcommencementVIkhởi công
The start of construction.
-
上棟 じょうとう
ENtopping outVIcất nóc
The milestone when the highest structural member is placed.
-
竣工 しゅんこう
ENcompletionVIhoàn công
Completion of all construction work.
-
引渡し ひきわたし
ENhandoverVIbàn giao
Transferring the finished building to the owner.
-
工程会議 こうていかいぎ
ENprogress meetingVIhọp giao ban công trường
A regular meeting coordinating progress among contractors.
-
工事請負契約 こうじうけおいけいやく
ENconstruction contractVIhợp đồng thi công
A contract where the contractor completes the works and the owner pays.
-
一括請負 いっかつうけおい
ENlump-sum contractVIhợp đồng trọn gói
A contract with a fixed total price for all the work.
-
入札 にゅうさつ
ENbiddingVIđấu thầu
Contractors submitting competing prices to win the work.
-
設計変更 せっけいへんこう
ENchange orderVIphát sinh (thay đổi thiết kế)
A design change after contract signing, adjusting price or schedule.
-
追加工事 ついかこうじ
ENadditional workVIcông việc phát sinh
Work outside the original contract scope.
-
出来高払い できだかばらい
ENprogress paymentVIthanh toán theo tiến độ
Payment for the quantity of work completed in a period.
-
契約不適合責任 けいやくふてきごうせきにん
ENdefect liabilityVItrách nhiệm bảo hành
Liability to fix work not conforming to the contract (formerly kashi tanpo).
-
建築確認 けんちくかくにん
ENbuilding permitVIgiấy phép xây dựng
Official confirmation that a design complies with the Building Standards Act.
-
建築基準法 けんちくきじゅんほう
ENBuilding Standards ActVILuật Tiêu chuẩn Xây dựng
Japan's law setting minimum standards for structure, fire safety and use of buildings.
-
検査 けんさ
ENinspectionVInghiệm thu (kiểm tra)
Checking completed work against drawings and standards.
-
配筋検査 はいきんけんさ
ENrebar inspectionVInghiệm thu cốt thép
Checking bar size, number, spacing and cover before concreting.
-
中間検査 ちゅうかんけんさ
ENinterim inspectionVInghiệm thu giai đoạn
A statutory inspection at an intermediate stage of construction.
-
完了検査 かんりょうけんさ
ENcompletion inspectionVInghiệm thu hoàn thành
A statutory inspection after completion before the building may be used.
-
自主検査 じしゅけんさ
ENself-inspectionVItự kiểm tra
The contractor's own quality check before inspection by the supervisor.
-
指摘事項 してきじこう
ENpunch listVIdanh sách tồn tại cần sửa
Defects identified during inspection that must be corrected.
-
手直し てなおし
ENreworkVIlàm lại
Fixing or redoing work that does not meet requirements.
-
品質管理 ひんしつかんり
ENquality controlVIquản lý chất lượng
Controlling work so it meets design and standard quality.
-
許容差 きょようさ
ENdimensional toleranceVIdung sai
The permitted deviation in dimensions from the design.
-
供試体 きょうしたい
ENtest pieceVImẫu thử bê tông
A concrete cylinder sampled at pouring for compressive testing.
-
受入検査 うけいれけんさ
ENacceptance inspectionVIkiểm tra khi nhận hàng
Checking materials or fresh concrete on delivery (slump, temperature, air content).
-
工事写真 こうじしゃしん
ENphoto recordVIảnh ghi nhận thi công
Photos with a labelled board as evidence of work, especially concealed parts.
-
作業日報 さぎょうにっぽう
ENdaily reportVInhật ký thi công
A daily record of work done, labour, equipment and incidents.
-
竣工図 しゅんこうず
ENas-built drawingsVIbản vẽ hoàn công
Drawings showing the building as actually constructed.
-
承認図 しょうにんず
ENsubmittalVIhồ sơ trình duyệt
Drawings or product data submitted for approval before work proceeds.
-
施工計画書 せこうけいかくしょ
ENconstruction planVIbiện pháp thi công
A document describing sequence, methods, equipment and safety for a work item.